Sector Education
Project type New build
Services provided Product / system manufacture
Year completed 2010
Project location South East England
Contract value (£) 2.6m
Client Cambridgeshire County Council
Consultant Capita Symonds – project manager Matthew Hucklesby
Contractor Morgan Ashurst; bricklaying subcontractor: Hall Contracts of Norfolk
Products used Standard Grade Plus Blocks 215mm, using the thin-joint system
 
 

Challenge

Sawston Village College used H+H UK’s Plus Blocks and the thin-joint system for its new science block extension. The extension provides eight new classrooms to develop the college’s specialism in teaching sciences to 11–16 year-olds.

The first phase – to create five classrooms over a 700m2 floor-space – was completed within 37 weeks by the Christmas holiday of 2008. The second phase – to create three classrooms over a 450m2 floor-space – was completed within 27 weeks, by the start of the summer holiday. The fittings and furnishings were installed during the holidays.

H+H UK’s Plus Blocks and the thin-joint system combine to make a fast-track construction programme, which meets the internal acoustic requirements while thermally insulating the external walls. After being used on the first phase, this construction method provided the advantage of speed against phase two’s summer holiday deadline.

Solution

Internal separating walls: 6m-high of solid aircrete blockwork to the pitched roof apex using 7N/mm2-rated Plus Block (610mmx215mmx200mm) and the thin-joint system. Murfor prefabricated stainless steel horizontal bedjoints every 2nd course. After using a three-coat plaster system at 6–8mm thickness on the first phase, the result was improved on the second phase by using a 10mm single coat spray plaster by Lafarge. Spray plaster applied beyond suspended ceiling levels to maintain acoustics.

External cavity walls: 6m-high cavity-construction walls using Plus Block (610 x 215 x 100mm) and the H+H thin-joint system with 17mm Kingspan Kooltherm insulation boards plus 100mm facing bricks. Stainless twist ties for lateral support within the 118mm cavity. Concrete ring beams on top spread the load for the 3.6N/mm2-strength Plus Blocks.

  • Production

H+H aircrete consists of 80% pulverised fuel ash waste recycled from power stations that would otherwise be destined for landfill.

  • Acoustic credentials

The walls are specified to achieve a minimum acoustic insulation level of 49dBRW, because the BB93 requirement is in the range of 40–45DnT (Tmf, max).

  • Thermal insulation

Having a 0.15W/m2K U-value for thermal insulation, enabled the external wall specification to be lenient in other details, such as the windows and doors. This thermal rating also enabled the external wall cavity to be narrower than for concrete breezeblocks, freeing up more floorspace.

  • Speed of build

The thin-joint system enables the structure to be erected faster and to a better quality, allowing follow-on trades to start work sooner in a weatherproof environment.

  • Health and safety

The aircrete product presents minimal risk on site, especially in terms of its light weight for manual handling. This is not only important to the builders, but also to the architects, because they are legally liable for the H&S of handling the specified products on site.

Outcome

There were many compelling reasons for choosing H+H aircrete products for this project. The system constitutes a modern method of construction (MMC), and the product has good credentials in terms of sustainability when it comes to production, waste control, packaging and delivery/transportation.

“While most masonry manufacturers claim general acoustic insulation performance for products in housing, quantifiable substantiation of their performances was difficult to pin down against the BB93 standard for schools. From this first experience of aircrete, I will certainly specify it for future projects.” Matthew Huckelsby, Project manager, Capita Symonds

“The Thin-Joint system’s mortar for each course dries within 10 minutes, so we are building the 6m-high walls much quicker than I’ve ever known for traditionally mortared concrete. I’ve been in the trade since 1973. The Thin-Joint mortar is also good for temperatures below that of traditional mortar, which was important during the especially cold winter.” Stuart Lovesey, Site manager, Morgan Ashurst

The clients found an additional use for the completed walls: aircrete is an acceptable direct substrate for the fixings of load-bearing fittings such as shelves and cupboards, as well as for heavy plant such as heaters.


Challenge

Sawston Village College used H+H UK’s Plus Blocks and the thin-joint system for its new science block extension. The extension provides eight new classrooms to develop the college’s specialism in teaching sciences to 11–16 year-olds.

The first phase – to create five classrooms over a 700m2 floor-space – was completed within 37 weeks by the Christmas holiday of 2008. The second phase – to create three classrooms over a 450m2 floor-space – was completed within 27 weeks, by the start of the summer holiday. The fittings and furnishings were installed during the holidays.

H+H UK’s Plus Blocks and the thin-joint system combine to make a fast-track construction programme, which meets the internal acoustic requirements while thermally insulating the external walls. After being used on the first phase, this construction method provided the advantage of speed against phase two’s summer holiday deadline.

Solution

Internal separating walls: 6m-high of solid aircrete blockwork to the pitched roof apex using 7N/mm2-rated Plus Block (610mmx215mmx200mm) and the thin-joint system. Murfor prefabricated stainless steel horizontal bedjoints every 2nd course. After using a three-coat plaster system at 6–8mm thickness on the first phase, the result was improved on the second phase by using a 10mm single coat spray plaster by Lafarge. Spray plaster applied beyond suspended ceiling levels to maintain acoustics.

External cavity walls: 6m-high cavity-construction walls using Plus Block (610 x 215 x 100mm) and the H+H thin-joint system with 17mm Kingspan Kooltherm insulation boards plus 100mm facing bricks. Stainless twist ties for lateral support within the 118mm cavity. Concrete ring beams on top spread the load for the 3.6N/mm2-strength Plus Blocks.

  • Production

H+H aircrete consists of 80% pulverised fuel ash waste recycled from power stations that would otherwise be destined for landfill.

  • Acoustic credentials

The walls are specified to achieve a minimum acoustic insulation level of 49dBRW, because the BB93 requirement is in the range of 40–45DnT (Tmf, max).

  • Thermal insulation

Having a 0.15W/m2K U-value for thermal insulation, enabled the external wall specification to be lenient in other details, such as the windows and doors. This thermal rating also enabled the external wall cavity to be narrower than for concrete breezeblocks, freeing up more floorspace.

  • Speed of build

The thin-joint system enables the structure to be erected faster and to a better quality, allowing follow-on trades to start work sooner in a weatherproof environment.

  • Health and safety

The aircrete product presents minimal risk on site, especially in terms of its light weight for manual handling. This is not only important to the builders, but also to the architects, because they are legally liable for the H&S of handling the specified products on site.

Outcome

There were many compelling reasons for choosing H+H aircrete products for this project. The system constitutes a modern method of construction (MMC), and the product has good credentials in terms of sustainability when it comes to production, waste control, packaging and delivery/transportation.

“While most masonry manufacturers claim general acoustic insulation performance for products in housing, quantifiable substantiation of their performances was difficult to pin down against the BB93 standard for schools. From this first experience of aircrete, I will certainly specify it for future projects.” Matthew Huckelsby, Project manager, Capita Symonds

“The Thin-Joint system’s mortar for each course dries within 10 minutes, so we are building the 6m-high walls much quicker than I’ve ever known for traditionally mortared concrete. I’ve been in the trade since 1973. The Thin-Joint mortar is also good for temperatures below that of traditional mortar, which was important during the especially cold winter.” Stuart Lovesey, Site manager, Morgan Ashurst

The clients found an additional use for the completed walls: aircrete is an acceptable direct substrate for the fixings of load-bearing fittings such as shelves and cupboards, as well as for heavy plant such as heaters.


Interested in this case study?
Call 01732 886333
OR
 
 
 
Downloads
  • Higher Strength Grade Blocks Data Sheet
    Higher Strength Grade Blocks Data Sheet
    2pp 1.19MB
    Download
  • Celcon Plus Blocks Data Sheet
    Celcon Plus Blocks Data Sheet
    2pp 759.99KB
    Download
  • Sawston College, Cambridge: Science Wing construction
    Sawston College, Cambridge: Science Wing construction
    3pp 923.59KB
    Download
  • Products & Applications Guide
    Products & Applications Guide
    5.76MB
    Download
 
 
 
Enquire
 


Related entries

  • H+H UK: Celcon Higher Strength Grade Blocks
    Celcon Higher Strength Grade Blocks
    H+H UK
    Celcon Higher Strength Grade aircrete is used principally where higher compressive strengths are required, such as foundations and lower storeys of three storey buildings, piers, under high vertical loads and multi-storey...
  • H+H UK: Light Gauge Steel vs Thin-joint Masonry
    Light Gauge Steel vs Thin-joint Masonry
    H+H UK
    Davis Langdon were commissioned by H+H UK Ltd to undertake a study to provide a detailed comparison between Light Gauge Steel (LGS) Frame construction and H+H UK Ltd thin-joint masonry construction using aircrete units. The...
  • H+H UK: Thin-joint system used for low energy apartment block
    Thin-joint system used for low energy apartment block
    H+H UK
    H+H’s Thin Joint system has been used in a fabric-first approach to the design and construction of a low energy apartment block on a constrained site in Brighton. The planners insisted the four-apartment scheme had to comply...
  • H+H UK: New robust details for Aircrete separating walls
    New robust details for Aircrete separating walls
    H+H UK
    Newly published Robust Details from H+H UK Ltd show that separating walls built using H+H aircrete blocks can easily surpass Building Regulation requirements, achieving the enhanced performances required for 3 credits under...
Not found what you're looking for? View other options

Ask H+H UK about

Sawston College, Cambridge: Science Wing construction