Sector Commercial
Project type New build
Services provided Site survey
Design
Product / system manufacture
Product / system supply
Project location South East England
Contract value (£) £5m
Client NWES
Contractor R G Carter
Products used B20 stair and balcony handrail system; B40 Frameless Glass balustrade with stainless steel slotted handrail
 
 

Context

King’s Lynn Innovation Centre has provided a contemporary look to the newest business hub within the Nar Ouse regeneration area.

The business centre is operated by the enterprise agency, NWES. NWES aims to provide local business support services including mentoring, one-to-one advice, workshops and financial support.

The King’s Lynn Innovation Centre provides West Norfolk with modern office space and conference suites. The centre is designed to empower business professionals and allow them to network and engage to enable economic growth in the King’s Lynn region.

The challenge

At the early stage, the structure of the building presented challenges for the balustrade installation:

  • The balustrade could not be fixed to the composite floor deck in the internal walkways.
  • The steel structure for the internal and external balcony areas was significantly lower than the finished floor level.
  • Clarification was needed on the loadings to ensure that the regulations were met without adversely affecting the final balustrade contract sum.

The solution

Following significant pre-contract design development, BA Systems were appointed by RG Carter to provide balustrade solutions.

The versatile stair and balcony handrail B20 system, with stainless steel posts and wire infills, was proposed for the internal voids and stair cores. To maintain the necessary 0.74kN/m loading in the walkway voids, the BA Systems technical team had to design a steel fixing plate. This plate was then welded onto the steel beam below the composite floor deck at an early stage so that once the wall finish had been applied, the 2-point balustrade post fixing could be installed.

RG Carter chose the minimalist B40 Frameless Glass balustrade with a stainless steel slotted handrail for the internal and external balconies to the main void area. In order to elevate the ICE1 balustrade channel off the steel beam, a steel box section was designed for the channel to be fixed to. This ensured that the top of the balustrade channel finished just above floor level. 21.5mm toughened and laminated clear glass was used to meet the specified 1.5kN/m walkway loading in this central area.

At execution stage, the Site Surveyor and Project Manager worked closely with the RG Carter site team to ensure that BA Systems balustrade works were synchronised with the surrounding trades. This was particularly important for the internal voids, where the early installation of the steel plates had a small window of installation time.


Context

King’s Lynn Innovation Centre has provided a contemporary look to the newest business hub within the Nar Ouse regeneration area.

The business centre is operated by the enterprise agency, NWES. NWES aims to provide local business support services including mentoring, one-to-one advice, workshops and financial support.

The King’s Lynn Innovation Centre provides West Norfolk with modern office space and conference suites. The centre is designed to empower business professionals and allow them to network and engage to enable economic growth in the King’s Lynn region.

The challenge

At the early stage, the structure of the building presented challenges for the balustrade installation:

  • The balustrade could not be fixed to the composite floor deck in the internal walkways.
  • The steel structure for the internal and external balcony areas was significantly lower than the finished floor level.
  • Clarification was needed on the loadings to ensure that the regulations were met without adversely affecting the final balustrade contract sum.

The solution

Following significant pre-contract design development, BA Systems were appointed by RG Carter to provide balustrade solutions.

The versatile stair and balcony handrail B20 system, with stainless steel posts and wire infills, was proposed for the internal voids and stair cores. To maintain the necessary 0.74kN/m loading in the walkway voids, the BA Systems technical team had to design a steel fixing plate. This plate was then welded onto the steel beam below the composite floor deck at an early stage so that once the wall finish had been applied, the 2-point balustrade post fixing could be installed.

RG Carter chose the minimalist B40 Frameless Glass balustrade with a stainless steel slotted handrail for the internal and external balconies to the main void area. In order to elevate the ICE1 balustrade channel off the steel beam, a steel box section was designed for the channel to be fixed to. This ensured that the top of the balustrade channel finished just above floor level. 21.5mm toughened and laminated clear glass was used to meet the specified 1.5kN/m walkway loading in this central area.

At execution stage, the Site Surveyor and Project Manager worked closely with the RG Carter site team to ensure that BA Systems balustrade works were synchronised with the surrounding trades. This was particularly important for the internal voids, where the early installation of the steel plates had a small window of installation time.


Interested in this project?
Call 01603 722330
OR
 
 
 
Downloads
 
 
 
Enquire
 


Related entries

  • BA Systems: B40 frameless glass balustrade system
    B40 frameless glass balustrade system
    BA Systems
    Enjoy uninterrupted views with this minimalist all-glass solution: provides effective, appealing edge protection; minimalist design maximises views and sunlight - no vertical supports or visible fixings; complementary...
  • BA Systems: B20 post and infill handrail system for stairs/balconies
    B20 post and infill handrail system for stairs/balconies
    BA Systems
    The B20 handrail system offers the following features: provides robust, aesthetically pleasing edge protection; cost effective while offering clarity and open views; choice of infill options for residential and commercial...
Not found what you're looking for? View other options

Ask BA Systems about

Modern handrail systems selected for new business hub